Current Status and Accomplishments
Completed Work:
Phase 1 Enhancements: (Texas Parks & Wildlife Grant)
Hi-Line Bridge Connector (2024): connects Katy Trail to Trinity Strand Trail through Victory Park and the Design District
Phase 2 Medical District Segments: $3.3M 2012 bond-funded extension through Parkland, Market Center, and Inwood DART Station
In Progress:
Hi-Line Pedestrian Bridge connecting Hi-Line to Phase 3
Phase 1 & 2 Enhancements: lighting, benches, fountains
Phase 3 planning